FIDIC - Red Book 1999 - Second Notice

Sub-clause 1.9 [Delayed Drawings or Instructions] of the FIDIC Red Book, First Edition 1999. The relevant sub-clause has very specific notification requirements which are not always properly complied with.

Below is an example of a draft template dealing with the second notification required in terms of this sub-clause 1.9 [Delayed Drawings or Instructions] for information. It should be noted that templates should be used with caution as any amendments to the general conditions of contract must also be considered.